[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101914":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101914,779,2,"多选题","（2020年真题）根据《标准设计施工总承包招标文件》中的通用合同条款，关于竣工验收的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人应提前14天将申请竣工试验通知送达发包人",false,{"key":16,"text":17,"correct":18},"B","承包人应在申请竣工试验前提交运行操作和维修手册",true,{"key":20,"text":21,"correct":14},"C","承包人应在竣工试验通过时将工程移交给发包人组织试运行",{"key":23,"text":24,"correct":18},"D","工程经验收合格，监理人经发包人同意后签发工程接收证书;",{"key":26,"text":27,"correct":18},"E","工程接收证书上注明的实际竣工日期为提交竣工验收申请报告的日期","BDE","P114-117 监理人应在收到竣工验收申请报告后的56 天内，向承包人出具经发包人签认的工程接收证书。以承包人提交竣工验收申请报告的日期为实际竣工日期，并在工程接收证书中写明。实际竣工日用以计算施工期限，与合同工期对照判定承包人是提前竣工还是延误竣工。 除了专用条款约定由发包人负责试运行的情况外，承包人应负责提供试运行所需的人员、器材和必要的条件，并承担全部试运行费用。施工期运行中发现工程或工程设备损坏或存在缺陷时，由承包人进行修复，并按照缺陷原因由责任方承担相应的费用。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]