[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101912":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101912,779,2,"多选题","（2020年真题）根据《标准施工招标文件》中的通用合同条款，发包人仅限于给予承包人费用补偿的情形有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","法规变化引起的价格调整",true,{"key":16,"text":17,"correct":18},"B","监理人的指示错误",false,{"key":20,"text":21,"correct":14},"C","因不可抗力停工期间的工程照管",{"key":23,"text":24,"correct":18},"D","发包人提供图纸延误",{"key":26,"text":27,"correct":18},"E","重新检验隐蔽工程质量","AC","P110-112",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]