[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101911":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101911,779,2,"多选题","（2020年真题）根据《标准施工招标文件》中的通用合同条款，施工中因（ ）引起的暂停施工，承包人有权要求延长工期、增加费用和支付合理利润。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","发包人负责提供的设备未按时到位",true,{"key":16,"text":17,"correct":14},"B","发包人委托的设计人提供的设计文件错误",{"key":19,"text":20,"correct":21},"C","发生不可抗力",false,{"key":23,"text":24,"correct":21},"D","承包人原因进行施工方案调整",{"key":26,"text":27,"correct":21},"E","承包人施工机械故障","AB","P99-102 通用条款中明确规定，由于发包人原因导致的延误，承包人有权获得工期顺延和（或）费用加利润补偿的情况包括: （1）增加合同工作内容; （2） 改变合同中任何一项工作的质量要求或其他特性; （3） 发包人迟延提供材料、工程设备或变更交货地点; （4） 因发包人原因导致的暂停施工; （5） 提供图纸延误; （6） 未按合同约定及时支付预付款、进度款; （7）发包人造成工期延误的其他原因。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]