[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101905":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101905,779,2,"多选题","(2016年真题)根据《标准施工合同》，工程施工中承包人有权获得费用补偿和工期延期，并获得合理利润的情形有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发现文物、化石等的处理",false,{"key":16,"text":17,"correct":18},"B","发包人改变合同中任何一项工作的质量要求",true,{"key":20,"text":21,"correct":18},"C","发包人未按合同约定及时支付工程进度款导致暂停施工",{"key":23,"text":24,"correct":18},"D","隐蔽工程重新检验质量合格",{"key":26,"text":27,"correct":14},"E","不可抗力事件发生后的清理工作","BCD","本题考查的是索赔管理。选项A只可索赔工期、费用；选项E只可索赔费用。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]