[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101900":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101900,779,2,"多选题","(2019年真题)根据《标准施工招标文件》的施工合同文本通用合同条款，规定因不可抗力造成的损失，由发包人承担的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","永久工程的损失",true,{"key":16,"text":17,"correct":18},"B","施工设备损坏",false,{"key":20,"text":21,"correct":18},"C","停工损失",{"key":23,"text":24,"correct":14},"D","施工场地的材料和工程设备",{"key":26,"text":27,"correct":18},"E","承包人的人员伤亡损失","AD","标准施工合同中应给承包人补偿的条款",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]