[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101899":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101899,779,2,"多选题","(2018)根据《标准施工合同》，属于发包人原因可以延长合同工期的情形有（ ）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","增加工作内容",true,{"key":16,"text":17,"correct":14},"B","提供图纸延误",{"key":19,"text":20,"correct":14},"C","出现异常恶劣的气候条件",{"key":22,"text":23,"correct":14},"D","发包人延迟提供建筑材料",{"key":25,"text":26,"correct":27},"E","现场查勘滞后",false,"ABCD","标准施工合同中应给承包人补偿的条款",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]