[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101897":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101897,779,2,"多选题","(2017年真题)根据《标准施工合同》，关于工程计量的说法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","单价子目已完工程量按月计量",true,{"key":16,"text":17,"correct":14},"B","总价子目的计量支付不考虑市场价格浮动",{"key":19,"text":20,"correct":21},"C","总价子目巳完工程量按月计量",false,{"key":23,"text":24,"correct":14},"D","总价子目表中标明的工程量通常不进行现场计量",{"key":26,"text":27,"correct":21},"E","总价子目表中标明的工程量通常不进行图纸计量","ABD","1.变更估价的程序 承包人应在收到变更指示或变更意向书后的14天内，向监理人提交变更报价书； 监理人收到承包人变更报价书后的14天内，根据合同约定的估价原则，商定或确定变更价格。 2.变更的估价原则 （1）已标价工程量清单中有适用于变更工作的子目，采用该子目的单价计算变更费用； （2）无适用于变更工作的子目，但有类似子目，可参照类似子目的单价，由监理人商定或确定单价； （3）已标价工程量清单中无适用或类似子目的单价，可按照成本加利润的原则，由监理人商定或确定单价。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]