[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101894":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101894,779,2,"多选题","(2019年真题)根据《标准施工招标文件》的施工合同文本通用合同条款，承包人竣工清场的主要义务有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","就交付工程的使用功能向发包人交接",false,{"key":16,"text":17,"correct":18},"B","拆除临时工程，清理，平整或复原场地",true,{"key":20,"text":21,"correct":14},"C","保证工程建筑物周边及其附近道路交通通畅",{"key":23,"text":24,"correct":18},"D","施工场地内承包人设备和剩余材料已按计划撤离现场",{"key":26,"text":27,"correct":18},"E","施工场地内残留垃圾已全部清除出场","BDE","（五）竣工清场（承包人进行清场） （1）施工场地内残留的垃圾已全部清除出场； （2）临时工程已拆除，场地已按合同要求进行清理、平整或复原； （3）按合同约定应撤离的承包人设备和剩余的材料，包括废弃的施工设备和材料，已按计划撤离施工场地； （4）工程建筑物周边及其附近道路、河道的施工堆积物，已按监理人指示全部清理； （5）监理人指示的其他场地清理工作已全部完成。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]