[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101884":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101884,779,2,"多选题","(2017年真题)施工准备阶段发包人的义务包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","现场查勘",false,{"key":16,"text":17,"correct":14},"B","提出开工申请",{"key":19,"text":20,"correct":21},"C","提供施工场地",true,{"key":23,"text":24,"correct":21},"D","组织设计交底",{"key":26,"text":27,"correct":21},"E","约定开工时间","CDE","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]