[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101872":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101872,779,2,"多选题","(2011年真题)工程师依据施工现场的下列情况向承包人发布暂停施工指令时，其中应顺延合同工期的情况有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","地基开挖遇到勘察资料未标明的断层，需要重新确定基础处理方案",true,{"key":16,"text":17,"correct":14},"B","发包人订购的设备未能按时到货",{"key":19,"text":20,"correct":21},"C","施工作业方法存在重大安全隐患",false,{"key":23,"text":24,"correct":14},"D","后续施工现场未能按时完成移民拆迁工作",{"key":26,"text":27,"correct":14},"E","施工中遇到有考古价值的文物需要采取保护措施予以保护","ABDE","（四）暂停施工 承包人责任引起的暂停施工，增加的费用和工期由承包人承担； 发包人暂停施工的责任，承包人有权要求发包人延长工期和（或）增加费用，并支付合理利润。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]