[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101871":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101871,779,2,"多选题","(2010年真题)导致现场发生暂停施工的下列情形中，承包商在执行工程师暂停施工的指示后，可以要求发包人追加合同价款并顺延工期的包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工作业方法可能危及邻近建筑物的安全",false,{"key":16,"text":17,"correct":18},"B","施工中遇到了有考古价值的文物",true,{"key":20,"text":21,"correct":18},"C","发包人订购的设备不能按时到货",{"key":23,"text":24,"correct":14},"D","施工作业危及人身安全",{"key":26,"text":27,"correct":18},"E","发包人未能按时移交后续施工的现场","BCE","（四）暂停施工 承包人责任引起的暂停施工，增加的费用和工期由承包人承担； 发包人暂停施工的责任，承包人有权要求发包人延长工期和（或）增加费用，并支付合理利润。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]