[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101864":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101864,779,2,"多选题","施工合同中，监理人职责中关于开工通知，说法正确的是（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","当发包人的开工前期工作已完成且临近约定的开工日期时，应委托监理人接专用条款约定的时间向承包人发出开工通知",true,{"key":16,"text":17,"correct":18},"B","如果约定的开工已届至但发包人应完成的开工配合义务尚未完成(如现场移交延误)，由于监理人不能按时发出开工通知，则合同工期不予顺延",false,{"key":20,"text":21,"correct":14},"C","如果发包人开工前的配合工作已完成且约定的开工日期已届至，但承包人的开工准备还不满足开工条件，监理人仍应按时发出开工的指示，合同工期不予顺延。",{"key":23,"text":24,"correct":14},"D","监理人征得发包人同意后，应在开工日期7天前向承包人发出开工通知",{"key":26,"text":27,"correct":18},"E","监理工程师发出开工通知后，合同工期自合同规定的开工日起计算","ACD","2020版教材P98-99 监理人征得发包人同意后，应在开工日期7 天前向承包人发出开了.通知，合同工期自开工通知中载明的开工日起计算。如果约定的开工已届至但发包人应完成的开工配合义务尚未完成(如现场移交延误) ，由于监理人不能按时发出开工通知，则要顺延合同工期并赔偿承包人的相应损失。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]