[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101859":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101859,779,2,"多选题","施工准备阶段发包人的义务包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","提供施工场地",true,{"key":16,"text":17,"correct":14},"B","组织设计交底",{"key":19,"text":20,"correct":21},"C","编制施工实施计划",false,{"key":23,"text":24,"correct":14},"D","约定开工时间",{"key":26,"text":27,"correct":21},"E","现场勘察","ABD","2020版教材P96-97 发包人的义务包括：(1)提供施工场地；(2)组织设计交底；(3)约定开工时间。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]