[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101854":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101854,779,2,"多选题","根据《施工合同》，合同进度计划的主要作用有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","监理人确认承包人逾期违约的依据",false,{"key":16,"text":17,"correct":14},"B","监理人签认索赔付款证书的依据",{"key":19,"text":20,"correct":21},"C","施工进度受到干扰后，监理人判定是否应顺延合同工期的依据",true,{"key":23,"text":24,"correct":14},"D","承包人编制资金计划的基础",{"key":26,"text":27,"correct":21},"E","监理人控制合同工程进度的依据","CE","2020版教材P98-99 本题考查的是监理人的职责。合同进度计划是控制合同工程进度的依据，对承包人、发包人和监理人均有约束力，不仅要求承包人按计划施工，还要求发包人的材料供应、图纸发放等不应造成施工延误，以及监理人应按照计划进行协调管理。合同进度计划的另一重要作用是，施工进度受到非承包人责任原因的干扰后，判定是否应给承包人顺延合同工期的主要依据。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]