[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101847":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101847,779,2,"多选题","下列有关确定变更价款的做法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","变更确定后承包人及时提出追加价款要求的报告",true,{"key":16,"text":17,"correct":14},"B","工程师在规定时间内对承包人的要求作出答复",{"key":19,"text":20,"correct":21},"C","确定的价款报送造价管理部门备案",false,{"key":23,"text":24,"correct":14},"D","监理人收到承包人的变更报价书后的14天内，商定或确定变更价格",{"key":26,"text":27,"correct":21},"E","承包人未提出追加价款报告，工程师可单独决定补偿额","ABD","2020版教材P108-110 本题考查的是变更管理。承包人应在收到变更指示或变更意向书后的14天内，向监理人提交变更报价书；监理人收到承包人的变更报价书后的14天内，根据合同约定的估价原则，商定或确定变更价格。监理人收到承包人的书面建议后，应与发包人共同研究，确认存在变更的，应在收到承包人书面建议后的14天内做出变更指示；经研究后不同意作为变更的，由监理人书面答复承包人。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]