[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101843":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101843,779,2,"多选题","施工过程中如果发包人要求提前竣工，应与承包商协商并签订提前竣工协议。根据《建设工程施工合同（示范文本）》，提前竣工协议书中应包括的内容有（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","承包人修订进度计划",true,{"key":16,"text":17,"correct":14},"B","发包人应提供的条件",{"key":19,"text":20,"correct":14},"C","承包人采取的赶工措施",{"key":22,"text":23,"correct":14},"D","提前竣工需追加的合同价款",{"key":25,"text":26,"correct":27},"E","承包人未能提前竣工的延误赔偿计算方法",false,"ABCD","2020版教材P102 如果发包人根据实际情况向承包人提出提前竣工要求，由于涉及合同约定的变更，应与承包人通过协商达成提前竣工协议作为合同文件的组成部分。协议的内容应包括：承包人修订进度计划及为保证工程质量和安全采取的赶工措施；发包人应提供的条件；所需追加的合同价款；提前竣工给发包人带来效益应给承包人的奖励等。专用条款使用说明中建议，奖励金额可为发包人实际效益的20%。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]