[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101841":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101841,779,2,"多选题","施工合同示范文本规定可以顺延工期的条件有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不可抗力",true,{"key":16,"text":17,"correct":18},"B","承包人的违约",false,{"key":20,"text":21,"correct":18},"C","施工机械发生故障",{"key":23,"text":24,"correct":14},"D","发包人延迟提供材料",{"key":26,"text":27,"correct":14},"E","提供图纸延误","ADE","2020版教材P100 本题考查的是施工进度管理。选项BC，属于承包人自身原因造成的工期延误，由承包人自行承担。 通用条款中明确规定，由于发包人原因导致的延误，承包人有权获得工期顺延和（或）费用加利润补偿的情况包括：（1）增加合同工作内容；（2）改变合同中任何一项工作的质量要求或其他特性；（3）发包人迟延提供材料、工程设备或变更交货地点；（4）因发包人原因导致的暂停施工；（5）提供图纸延误；（6）未按合同约定及时支付预付款、进度款；（7）发包人造成工期延误的其他原因。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]