[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101832":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101832,779,2,"多选题","下列有关隐蔽工程与重新检验提法中正确的有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","承包人自检后书面通知工程师验收",true,{"key":16,"text":17,"correct":14},"B","工程师接到承包人的通知后，应在约定的时间与承包人共同检验",{"key":19,"text":20,"correct":14},"C","若工程师未能按时提出延期检验要求，又未能按时参加验收，承包人可自行检验",{"key":22,"text":23,"correct":24},"D","若工程师已经在验收合格记录上签字，只有当有确切证据证明工程有问题的情况下才能要求承包人对已隐蔽的工程进行重新检验",false,{"key":26,"text":27,"correct":14},"E","重新检验如果不合格，应由承包人承担全部费用，工期不予顺延","ABCE","2020版教材P103 本题考查的是隐蔽工程与重新检验。选项D，监理人对已覆盖的隐蔽工程部位质量有疑问时，可要求承包人对已覆盖的部位进行钻孔探测或揭开重新检验，承包人应遵照执行。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]