[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101831":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101831,779,2,"多选题","按照施工合同内不可抗力条款的规定，下列事件中属于不可抗力的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","龙卷风导致吊车倒塌",true,{"key":16,"text":17,"correct":14},"B","地震导致主体建筑物的开裂",{"key":19,"text":20,"correct":21},"C","承包人管理不善导致的仓库爆炸",false,{"key":23,"text":24,"correct":21},"D","承包人拖欠雇员工资导致的动乱",{"key":26,"text":27,"correct":14},"E","非发包人和承包人责任发生的火灾","ABE","2020版教材P110 本题考查的是不可抗力。不可抗力，是指合同当事人不能预见、不能避免并且不能克服的客观情况。建设工程中的不可抗力包括因战争、动乱、空中飞行物坠落或其他非发包人和承包人责任造成的爆炸、火灾以及专用条款约定的风、雨、雪、洪水、地震等自然灾害。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]