[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101829":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101829,779,2,"多选题","根据标准施工合同的通用条款规定，下列关于合同进度计划的管理，说法正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","如果工程实际进度滞后于计划进度，应修订合同进度计划",true,{"key":16,"text":17,"correct":18},"B","如果工程实际进度超前于计划进度，不用修订合同进度计划",false,{"key":20,"text":21,"correct":14},"C","承包人可以主动修订合同进度计划，报监理人审批",{"key":23,"text":24,"correct":18},"D","监理人也可以修订合同进度计划，指示承包人遵照执行",{"key":26,"text":27,"correct":14},"E","监理人应在约定期限内对修订合同进度计划的申请报告予以批复","ACE","（一）合同进度计划的动态管理 1、只要工程的实际进度与合同进度计划不符，包括实际进度超前或滞后于计划进度，均应修订合同进度计划。 2、承包人可以主动向监理人提交修订合同进度计划的申请报告，并附有关措施和相关资料，报监理人审批；监理人也可以向承包人发出修订合同进度计划的指示，承包人应按该指示修订合同进度计划后报监理人审批。 3、监理人应在专用合同条款约定的期限内予以批复。如果修订的合同进度计划对竣工时间有较大影响或需要补偿额超过监理人独立确定的范围时，在批复前应取得发包人同意。（监理人：不编制、不修改-可指示修改、审查、提出修改意见）",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]