[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101824":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101824,779,2,"多选题","承包人未通知监理人到场检查，私自将工程隐蔽部位进行了覆盖，监理人指示承包人揭开检查，检查影响了正常施工。如结果表明质量合格，则（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","增加的费用由承包人承担",true,{"key":16,"text":17,"correct":18},"B","增加的费用由发包人承担",false,{"key":20,"text":21,"correct":18},"C","增加的费用由监理人承担",{"key":23,"text":24,"correct":18},"D","工期给予顺延",{"key":26,"text":27,"correct":14},"E","工期不予顺延","AE","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]