[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101822":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101822,779,2,"多选题","下列（）情形导致工期顺延，原定竣工日后的支付过程中，调价公式继续有效。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不可抗力事件的影响",true,{"key":16,"text":17,"correct":18},"B","承包人采购的施工材料未按时交货",false,{"key":20,"text":21,"correct":14},"C","施工许可证没有及时颁发",{"key":23,"text":24,"correct":14},"D","发包人原因不具备合同约定的开工条件",{"key":26,"text":27,"correct":14},"E","发包人迟延提供材料","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]