[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101819":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101819,779,2,"多选题","如果承包人认为发包人提供的图纸和文件存在属于变更范围的情形，则下列说法正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人可以直接实施变更",false,{"key":16,"text":17,"correct":18},"B","承包人应当向监理人提出书面变更建议",true,{"key":20,"text":21,"correct":14},"C","承包人应当向监理人提出书面变更建议后直接实施变更",{"key":23,"text":24,"correct":14},"D","监理人应当同意承包人提出的变更建议",{"key":26,"text":27,"correct":18},"E","监理人确认存在变更后，应在收到承包人书面变更建议后的14天内做出变更指示","BE","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]