[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101813":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101813,779,2,"多选题","根据《标准施工招标文件》的施工合同文本通用合同条款，“暂估价”和“暂列金额”的主要区别有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","是否列入已标价的工程量清单",false,{"key":16,"text":17,"correct":18},"B","是否在招标阶段已经确定价格",true,{"key":20,"text":21,"correct":18},"C","是否在合同履行阶段必然发生",{"key":23,"text":24,"correct":18},"D","承包人是否必然获得支付",{"key":26,"text":27,"correct":14},"E","是否包括在签约合同价内","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]