[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101812":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101812,779,2,"多选题","在合同履行阶段确定暂估价内的工程材料、设备或专业工程施工的最终价格，方法正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","属于依法必须招标的项目，按招标的中标价确定",true,{"key":16,"text":17,"correct":18},"B","未达到必须招标的规模或标准时，承包人负责提供的材料和设备，由承包人确定价格",false,{"key":20,"text":21,"correct":18},"C","未达到必须招标的规模或标准时，承包人负责提供的材料和设备，由供应商确定价格",{"key":23,"text":24,"correct":14},"D","未达到必须招标的规模或标准时，承包人负责提供的材料和设备，由监理人确认价格",{"key":26,"text":27,"correct":14},"E","未达到必须招标的规模或标准时，专业工程施工的价格由监理人进行估价确定","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]