[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101807":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101807,779,2,"多选题","对于承包商提出的索赔，可能同时给予补偿工期、费用和利润的情况有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对竣工检验的干扰",true,{"key":16,"text":17,"correct":18},"B","不可抗力造成的损失",false,{"key":20,"text":21,"correct":14},"C","延误移交施工现场",{"key":23,"text":24,"correct":14},"D","非承包商原因检验导致施工延误",{"key":26,"text":27,"correct":14},"E","业主提前占用工程","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]