[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101806":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101806,779,2,"多选题","仅给予承包人工期和费用补偿而不补偿利润的事件有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","延误移交施工现场",false,{"key":16,"text":17,"correct":18},"B","不可预见的外界条件",true,{"key":20,"text":21,"correct":18},"C","施工遇到文物和古迹",{"key":23,"text":24,"correct":14},"D","后续法规的调整",{"key":26,"text":27,"correct":14},"E","不可抗力事件造成的损害","BC","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]