[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101804":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101804,779,2,"多选题","下列关于合同工程竣工验收的说法中，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","监理人认为已具备竣工验收条件，应在收到竣工验收申请报告后的28天内提请发包人进行工程验收",true,{"key":16,"text":17,"correct":18},"B","竣工验收合格，应在监理人收到竣工验收申请报告后的56天内，由发包人向承包人出具工程接收证书",false,{"key":20,"text":21,"correct":14},"C","竣工验收基本合格但提出了需要整修和完善要求时，监理人应指示承包人限期修好，并缓发工程接收证书",{"key":23,"text":24,"correct":14},"D","竣工验收不合格，承包人在完成不合格工程的返工重作或补救工作后，应重新提交竣工验收申请报告",{"key":26,"text":27,"correct":18},"E","发包人在收到承包人竣工验收申请报告56天后未进行验收，视为验收不合格","ACD","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]