[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101802":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101802,779,2,"多选题","发生发包人违反合同规定的情况时，下列处理方法不正确的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","承包人立即解除合同",true,{"key":16,"text":17,"correct":14},"B","监理人发出通知要求纠正",{"key":19,"text":20,"correct":14},"C","承包人立即暂停施工",{"key":22,"text":23,"correct":24},"D","承包人发出通知要求纠正未果后暂停施工",false,{"key":26,"text":27,"correct":14},"E","暂停施工14天后发包人仍不纠正违约行为时解除合同","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]