[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101801":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101801,779,2,"多选题","下列关于工程设备试运行组织责任的说法中，正确是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","由承包人负责组织",true,{"key":16,"text":17,"correct":18},"B","由发包人负责组织",false,{"key":20,"text":21,"correct":18},"C","由监理人负责组织",{"key":23,"text":24,"correct":18},"D","发包人采购的设备试运行费用由发包人承担",{"key":26,"text":27,"correct":14},"E","承包人担全部试运行费用","AE","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]