[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101800":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101800,779,2,"多选题","下列关于工程竣工日期的说法中，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","竣工验收合格，但当事人对实际竣工日期有争议，以竣工验收合格日为竣工日期",true,{"key":16,"text":17,"correct":18},"B","竣工验收基本合格，以监理人复查承包人整修和完善工作达到了要求时为竣工日期",false,{"key":20,"text":21,"correct":14},"C","竣工验收不合格，重新验收合格后，以重新提交竣工验收申请报告日为竣工日期",{"key":23,"text":24,"correct":14},"D","发包人延误竣工验收的，以提交竣工验收申请报告日为竣工日期",{"key":26,"text":27,"correct":18},"E","承包人提交竣工验收报告前，发包人擅自使用，施工合同对此未作约定时，以提交竣工验收申请报告日为竣工日期","ACD","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]