[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101793":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101793,779,2,"多选题","根据建设工程施工合同示范文本的规定，因不可抗力事件导致的下列损失中，应由发包人承担的包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程本身的损失",true,{"key":16,"text":17,"correct":14},"B","承包人采购的运至施工现场待安装工程设备的损失",{"key":19,"text":20,"correct":21},"C","工程的人员伤亡损失",false,{"key":23,"text":24,"correct":21},"D","工程停工损失",{"key":26,"text":27,"correct":21},"E","承包人的施工机械损失","AB","发包人和承包人各自承担其人员伤亡和其他财产损失及其相关费用；停工损失由承包人承担，但停工期间应监理人要求照管工程和清理、修复工程的金额由发包人承担。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]