[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101792":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101792,779,2,"多选题","施工阶段发包人应在解除合同后28d内向承包人支付的金额有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","合同解除日以前所完成工作的价款",true,{"key":16,"text":17,"correct":14},"B","由于解除合同应赔偿的承包人损失",{"key":19,"text":20,"correct":21},"C","承包人为该工程施工订购并已付款的材料、工程设备和其他物品的金额，发包人付款后，该材料、工程设备和其他物品仍归承包人所有",false,{"key":23,"text":24,"correct":14},"D","承包人为完成工程所发生的，而发包人未支付的金额",{"key":26,"text":27,"correct":14},"E","承包人撤离施工场地以及遣散承包人人员的赔偿金额","ABDE","2020版教材P112-114 发包人应在解除合同后28d内向承包人支付下列金额：(1)合同解除日以前所完成工作的价款；(2)承包人为该工程施工订购并已付款的材料、工程设备和其他物品的金额。发包人付款后，该材料、工程设备和其他物品归发包人所有；(3)承包人为完成工程所发生的，而发包人未支付的金额；(4)承包人撤离施工场地以及遣散承包人人员的赔偿金额；(5)由于解除合同应赔偿的承包人损失；(6)按合同约定在合同解除日前应支付给承包人的其他金额。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]