[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101788":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101788,779,2,"多选题","《标准施工合同》中，承包人可以获得工期补偿的情形包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不可抗力停工期间的照管和后续清理",false,{"key":16,"text":17,"correct":18},"B","因发包人违约承包人暂停施工",true,{"key":20,"text":21,"correct":18},"C","增加合同工作内容",{"key":23,"text":24,"correct":18},"D","发包人原因导致工程质量缺陷",{"key":26,"text":27,"correct":18},"E","未按合同约定及时支付预付款、进度款","BCDE","2020版教材P110-112 本题考核的是承包人可以获得工期补偿的情形。不可抗力停工期间的照管和后续清理，只能获得费用补偿，无法获得工期和利润补偿，B、C、D、E四个选项均可以获得工期、费用和利润的补偿。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]