[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101783":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101783,779,2,"多选题","关于暂估价和暂列金额的说法，错误的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","暂估价用于支付必然发生但暂时不能确定的金额",false,{"key":16,"text":17,"correct":14},"B","暂列金额用于在签订协议书时不可预见变更的金额",{"key":19,"text":20,"correct":21},"C","暂估价包括以计日工方式支付的款项",true,{"key":23,"text":24,"correct":21},"D","暂估价属于签约合同价，而暂列金额不属于",{"key":26,"text":27,"correct":14},"E","承包人不一定能够全部获得暂列金额的支付","CD","2020版教材P104-107 本题考查的是工程款支付管理。暂列金额指己标价工程量清单中所列的一笔款项，用于在签订协议书时尚未确定或不可预见变更的施工及其所需材料、工程设备、服务等的金额，包括以计日工方式支付的款项。上述两笔款项均属于包括在签约合同价内的金额。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]