[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101782":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101782,779,2,"多选题","导致现场发生暂停施工的下列情形中，承包商在执行工程师暂停施工的指示后，可以要求发包人追加合同价款并顺延工期的包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工作业方法可能危及邻近建筑物的安全",false,{"key":16,"text":17,"correct":18},"B","施工中遇到了有考古价值的文物",true,{"key":20,"text":21,"correct":18},"C","发包人订购的设备不能按时到货",{"key":23,"text":24,"correct":14},"D","施工作业危及人身安全",{"key":26,"text":27,"correct":18},"E","发包人未能按时移交后续施工的现场","BCE","本题考查的是施工进度管理。非承包人原因既拖延了工期，又带来了经济上的损失，按此标准选择。选项AD为承包人原因。选项CE为发包人原因，选项B为客观情况，均非承包人原因。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]