[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101779":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101779,779,2,"多选题","根据《标准施工招标文件》的通用合同条款，可以同时给承包人工期和费用补偿的情形有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","监理人的指示延误",false,{"key":16,"text":17,"correct":18},"B","施工场地发现文物、化石",true,{"key":20,"text":21,"correct":14},"C","不可抗力不能按期竣工",{"key":23,"text":24,"correct":18},"D","不利的物质条件",{"key":26,"text":27,"correct":14},"E","附加浮动引起的价格调整","BD","2020版教材P110-112 本题考核的是可以给承包人补偿的条款。选项A可得到工期、费用和利润的补偿。选项C只可得到工期补偿。选项E只可得到费用补偿。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]