[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101778":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101778,779,2,"多选题","施工阶段发包人违约的情况包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人原因造成停工的持续时间超过28d",false,{"key":16,"text":17,"correct":18},"B","发包人拖延、拒绝批准付款申请和支付凭证，导致付款延误",true,{"key":20,"text":21,"correct":18},"C","发包人无法继续履行或明确表示不履行或实质上已停止履行合同",{"key":23,"text":24,"correct":18},"D","监理人无正当理由没有在约定期限内发出复工指示，导致承包人无法复工",{"key":26,"text":27,"correct":18},"E","发包人未能按合同约定支付预付款或合同价款","BCDE","2020版教材P112-114 本题考核的是施工阶段发包人违约的情况。施工阶段发包人违约的情况包括：(1)发包人未能按合同约定支付预付款或合同价款，或拖延、拒绝批准付款申请和支付凭证，导致付款延误；(2)发包人原因造成停工的持续时间超过56d以上；(3)监理人无正当理由没有在约定期限内发出复工指示，导致承包人无法复工；(4)发包人无法继续履行或明确表示不履行或实质上已停止履行合同；(5)发包人不履行合同约定的其他义务。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]