[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101777":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101777,779,2,"多选题","工程移交发包人运行后，缺陷责任期内出现的工程质量缺陷可能是承包人的施工质量原因，也可能属于非承包人应负责的原因导致。应由（ ）共同查明原因，分清责任。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设计人",false,{"key":16,"text":17,"correct":18},"B","监理人",true,{"key":20,"text":21,"correct":18},"C","发包人",{"key":23,"text":24,"correct":14},"D","勘察人",{"key":26,"text":27,"correct":18},"E","承包人","BCE","2020版教材P117-118 本题考核的是缺陷责任。工程移交发包人运行后，缺陷责任期内出现的工程质量缺陷可能是承包人的施工质量原因，也可能属于非承包人应负责的原因导致。应由监理人与发包人和承包人共同查明原因，分清责任。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]