[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101772":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101772,779,2,"多选题","按照施工合同范本通用条件的规定，经工程师确认后工期相应顺延的情形包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","奥运会期间按政府要求承包人暂停施工",true,{"key":16,"text":17,"correct":14},"B","发包人不能按约定日期支付工程预付款、进度款，致使工程不能正常进行",{"key":19,"text":20,"correct":14},"C","工程师未按合同约定提供所需指令、批准等，致使施工不能正常进行",{"key":22,"text":23,"correct":14},"D","同时在现场的两个承包人发生施工干扰，监理人从整体协调考虑，指示某一承包人暂停施工",{"key":25,"text":26,"correct":27},"E","承包人的施工机械故障使得工期延误",false,"ABCD","2020版教材P99-102 可以顺延合同工期的情况：1.发包人原因延长合同工期；2. 异常恶劣的气候条件。发包人责任的暂停施工：1)发包人未履行合同规定的义务。2) 不可抗力。3) 协调管理原因。4）行政管理部门的指令（A项）。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]