[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101771":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101771,779,2,"多选题","下列在施工阶段发生的事件中，可以顺延工期的情况包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不可抗力事件的影响",true,{"key":16,"text":17,"correct":18},"B","承包人采购的施工材料未按时交货",false,{"key":20,"text":21,"correct":14},"C","施工许可证没有及时颁发",{"key":23,"text":24,"correct":18},"D","不具备合同约定的开工条件",{"key":26,"text":27,"correct":14},"E","监理人未按合同约定提供所需指令","ACE","2020版教材P99-102 本题考查的是施工进度管理。通用条款中明确规定，由于发包人原因导致的延误，承包人有权获得工期顺延和(或)费用加利润补偿的情况包括：(1)增加合同工作内容；(2)改变合同中任何一项工作的质量要求或其他特性；(3)发包人迟延提供材料、工程设备或变更交货地点；(4)因发包人原因导致的暂停施工；(5)提供图纸延误；(6)未按合同约定及时支付预付款、进度款；(7)发包人造成工期延误的其他原因 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]