[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101769":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101769,779,2,"多选题","施工中若发包人出于某种考虑要求提前竣工，发包人要( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","负责修改施工进度计划",false,{"key":16,"text":17,"correct":14},"B","向承包人直接发出提前竣工的指令",{"key":19,"text":20,"correct":21},"C","与承包人协商并签订提前竣工协议",true,{"key":23,"text":24,"correct":21},"D","为承包人提供赶工的便利条件",{"key":26,"text":27,"correct":14},"E","减少对工程质量的检测试验","CD","2020版教材P99-102 本题考查的是施工进度管理。如果发包人根据实际情况向承包人提出提前竣工要求，由于涉及合同约定的变更，应与承包人通过协商达成提前竣工协议作为合同文件的组成部分。协议的内容应包括:承包人修订进度计划及为保证工程质量和安全采取的赶工措施;发包人应提供的条件;所需追加的合同价款;提前竣工给发包人带来效益应给承包人的奖励等。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]