[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101768":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101768,779,2,"多选题","施工合同示范文本规定，因( )等原因导致竣工时间延长．经监理人确认后可以顺延工期。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","不可抗力",true,{"key":16,"text":17,"correct":14},"B","工程量增加",{"key":19,"text":20,"correct":21},"C","承包商基础施工超挖",false,{"key":23,"text":24,"correct":14},"D","设计变更",{"key":26,"text":27,"correct":14},"E","监理人延误提供所需指令","ABDE","2020版教材P99-102 本题考查的是施工进度管理。可以顺延合同工期的情况：异常恶劣的气候条件和发包人原因。其中发包人原因包括：(1)增加合同工作内容；(2)改变合同中任何一项工作的质量要求或其他特性；(3)发包人迟延提供材料、工程设备或变更交货地点；(4)因发包人原因导致的暂停施工；(5)提供图纸延误；(6)未按合同约定及时支付预付款、进度款；(7)发包人造成工期延误的其他原因 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]