[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101767":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101767,779,2,"多选题","施工合同示范文本规定可以顺延工期的条件有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不可抗力",true,{"key":16,"text":17,"correct":18},"B","承包人的违约",false,{"key":20,"text":21,"correct":18},"C","施工机械发生故障",{"key":23,"text":24,"correct":14},"D","发包人延迟提供材料",{"key":26,"text":27,"correct":14},"E","提供图纸延误","ADE","2020版教材P99-102 本题考查的是施工进度管理。可以顺延合同工期的情况：1.发包人原因延长合同工期。2. 异常恶劣的气候条件；不可抗力的停工损失属于发包人应承担的风险。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]