[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101766":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101766,779,2,"多选题","下列关于暂停施工程序说法正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","无论何种情况的停工，监理人应与发包人和承包人协商",false,{"key":16,"text":17,"correct":18},"B","当工程具备复工条件时，监理人应立即向承包人发出复工通知",true,{"key":20,"text":21,"correct":18},"C","承包人无故拖延和拒绝复工，由此增加的费用和工期延误由承包人承担",{"key":23,"text":24,"correct":18},"D","承包人收到复工通知后，应在指示的期限内复工",{"key":26,"text":27,"correct":14},"E","因发包人原因无法按时复工时，承包人只可索赔费用","BCD","2020版教材P99-102 本题考查的是施工进度管理。(1)停工。监理人根据施工现场的实际情况，认为必要时可向承包人发出暂停施工的指示，承包人应按监理人指示暂停施工。不论由于何种原因引起的暂停施工，监理人应与发包人和承包人协商，采取有效措施积极消除暂停施工的影响。暂停施工期间由承包人负责妥善保护工程并提供安全保障。(2)复工。当工程具备复工条件时，监理人应立即向承包人发出复工通知，承包人收到复工通知后，应在指示的期限内复工。承包人无故拖延和拒绝复工，由此增加的费用和工期延误由承包人承担。因发包人原因无法按时复工时，承包人有权要求延长工期和(或)增加费用，以及合理利润 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]