[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101763":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101763,779,2,"多选题","关于缺陷责任期的说法，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","缺陷责任期自申请竣工之日起计算",false,{"key":16,"text":17,"correct":18},"B","缺陷责任期满，包括延长的期限终止后14天内，监理人出具经发包人签认的缺陷责任期终止证书",true,{"key":20,"text":21,"correct":18},"C","结清单生效即表明合同终止",{"key":23,"text":24,"correct":14},"D","发包人应在最终结清证书后28天内，将应支付款支付给承包人",{"key":26,"text":27,"correct":18},"E","对于工程主要部位承包人责任的缺陷工程修复后，缺陷责任期相应延长","BCE","2020版教材P117-118 本题考查的是缺陷责任期管理。选项A，缺陷责任期自实际竣工日期起计算。选项D，发包人应在最终结清证书后14天内，将应支付款支付给承包人 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]