[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101761":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101761,779,2,"多选题","以下对索赔的表述中，正确的有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","索赔的要求不需经对方同意",true,{"key":16,"text":17,"correct":14},"B","承包人应在发出索赔意向通知书后28天内，向监理人递交正式的索赔通知书",{"key":19,"text":20,"correct":14},"C","承包人应在索赔影响结束后的28天内递交最终索赔通知书",{"key":22,"text":23,"correct":14},"D","承包人接受索赔处理结果，发包人应在做出索赔处理结果答复后28天内完成赔付",{"key":25,"text":26,"correct":27},"E","承包人必须执行监理人的索赔处理决定",false,"ABCD","2020版教材P110-112 本题考查的是索赔管理。选项E，监理人应首先通过与当事人双方协商争取达成一致，分歧较大时在协商基础上确定索赔的金额和缺陷责任期延长的时间。承包人不接受索赔处理结果的，按合同争议解决 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]