[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101760":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101760,779,2,"多选题","竣工阶段发包人接受了承包人提交并经监理人签认的竣工付款证书后，承包人不能再对（ ）的事项提出索赔要求。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工阶段",true,{"key":16,"text":17,"correct":14},"B","竣工阶段",{"key":19,"text":20,"correct":21},"C","设计阶段",false,{"key":23,"text":24,"correct":21},"D","缺陷责任期",{"key":26,"text":27,"correct":21},"E","保修期","AB","2020版教材P110-112 本题考查的是索赔管理。竣工阶段发包人接受了承包人提交并经监理人签认的竣工付款证书后，承包人不能再对施工阶段、竣工阶段的事项提出索赔要求。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]