[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101759":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101759,779,2,"多选题","下列事件发生后既可以索赔费用又可以索赔利润的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","异常恶劣的气候条件",false,{"key":16,"text":17,"correct":14},"B","法规变化引起的价格调整",{"key":19,"text":20,"correct":21},"C","发包人原因试运行失败，承包人修复",true,{"key":23,"text":24,"correct":21},"D","发包人提前占用工程导致承包人费用增加",{"key":26,"text":27,"correct":21},"E","提供图纸延误","CDE","2020版教材P110-112 本题考查的是索赔管理。根据标准施工合同中应给承包人补偿的条款 表6-2 ： 选项A，异常恶劣的气候条件只能索赔工期；选项B，法规变化引起的价格调整只能索赔费用。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]