[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101758":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101758,779,2,"多选题","根据标准施工合同的规定，下列可以事件中，承包人可以索赔工期、费用和利润的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工中遇到地下文物、化石",false,{"key":16,"text":17,"correct":18},"B","监理人的指示延误",true,{"key":20,"text":21,"correct":18},"C","基准资料错误",{"key":23,"text":24,"correct":18},"D","隐蔽工程重新检验质量合格",{"key":26,"text":27,"correct":14},"E","不可抗力不能按期竣工","BCD","2020版教材P110-112 本题考查的是索赔管理。根据标准施工合同中应给承包人补偿的条款 表6-2 选项A，可以索赔工期和费用。选项E，只能索赔工期。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]